For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is________________?
Options:
Answer:
For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is dry rolling, application of screening, wet rolling and application of filler.