A project is handed over to the parent department after:
Options:
Explanation:
A project is typically handed over to the parent department after the issuance of a completion certificate, which confirms that the project has been completed as per the specifications, standards, and contractual requirements. The certificate signifies that the project is ready for use or occupancy.
Answer:
A project is handed over to the parent department after: Issuance of completion certificate.