Question #72149

Considering dual rate method, if employees work for 8500 budgeted hours at $120 per hour, and work for 9500 actual hours at $110 per hour, then the total cost would be ____________?


Options:

Answer: Considering dual rate method, if employees work for 8500 budgeted hours at $120 per hour, and work for 9500 actual hours at $110 per hour, then the total cost would be ,065,000.