Question #141019

If 8 people work for 60 days, how many days will it take for 6 people to complete the same work?


Options:

Tags: Math
Answer: If 8 people work for 60 days, how many days will it take for 6 people to complete the same work 80 days.

Test Your Knowledge

Want to practice more questions like this? Take a quiz in this category!

Take a Quiz

Share This Question